Welcome to the official website of Zhengzhou Far East Machinery Manufacturing Co., Ltd!
Zhengzhou Yuandong Machinery Manufacturing Co., Ltd.Provide you with high-quality construction machinery and technical consultation!
Telphone:400-651-1108 Whatsapp:+8618538097305 +8618538093952
Contact Us

Tel:400-651-1108 Whatsapp:+8618538097305 +8618538093952
Email:jack@zzydjx.net
Address:Like Village, Chengguan Township, Xingyang City, Henan Province
Contacts:Mr. Chen
Your location : Homepage > News > company news
company news

Concrete batching plant safety production emergency plan - water and power failure prevention

時(shí)間(jiān):2022-04-19 09:30:13 作(zuò)者:遠東 點擊:

In order to ensure that the concrete batching plant can operate in an orderly manner, and in case of emergencies, the concrete can be supplied normally and the batching plant can be operated normally. The technicians of Zhengzhou Yuandong Machinery specially summarized the emergency plan for the safety production of the concrete batching plant - water cut off. Power outage prevention measures, if there is a special situation, an emergency plan can be started immediately to solve it.


Contingency plan for safety production of concrete batching plant - water cutoff preventive measures

(1) The two production lines are equipped with an underground water storage tank that can store 70t of water, and a backup water storage tank that can store 200t of water. Before production, both the water storage tank and the backup water storage tank of the batching plant are controlled by the automatic control system, and the water tank is in a full state; at the same time, when the two water tanks are pumped or the water level of the rated water storage volume changes, the control system will start to work , keep storing water until the water tank is full.


(2) The water consumption per square of concrete is about 140kg. If the two production lines are running at the same time, the normal production volume is about 126m3/h, and the water consumption per hour is about 17.6t. In the event of a sudden water failure during construction, the water storage in the mixing station pool and the water storage tank in the backup tank can meet the production of 1900m3 of concrete, which can ensure the normal production of one day and the time required for emergency repairs to eliminate the water failure.


Concrete batching plant safety production emergency plan - power failure prevention measures

(1) If there is a sudden power outage during normal production, the person in charge of the shift should immediately contact the production dispatcher or the on-site electrician on duty, and the electrician on duty should rush to the power transformation and distribution room as soon as possible to find out the cause of the outage (at the same time, the electromechanical shift should arrange for the generator driver to be in place, Make preparations before power generation), distinguish whether the external power grid is out of power or the power distribution facilities are faulty.


(2) The standby power supply in the station is 2 diesel generators with an installed power of 200KW, which will start the power supply for the concrete mixing station in the event of a power failure. In order to ensure production, the office and living areas are generally not temporarily powered.


(3) Before starting the backup power supply, the electrician must first cut off the main isolation switch in the main power distribution cabinet, and the generator driver should check again whether all parts of the generator set are normal. After the generator driver and electrician check that the parameters of each part are normal and the conditions for power transmission are met, the electrician will perform the switching operation to send the power out.


(4) In order to ensure the normal and reliable operation of the standby power supply at any time, the equipment department has formulated a relevant standby power supply management system, implemented a strict management system for the generator set, and requires the custodial driver to perform a walk-in maintenance once a week to keep abreast of the power generation. If there is any abnormal phenomenon, it will be eliminated in time, and it will never run with illness; in addition, the driver should start the generator 1 hour in advance and run for 15 minutes before filling the bridge every day to confirm whether the generator is normal.


(5) The electromechanical team should make a monthly purchase plan for various accessories according to the maintenance and repair of the generator set and concrete mixing station every month to ensure the storage of wearing parts.


Through the above-shared concrete batching plant safety production emergency plan - water and power outage measures, it is hoped that manufacturers can pay more attention to preventing emergencies.